Process & Schedules

Catalyst filed the Notice of Intent and Pre-Application Document (PAD) to initiate the relicensing process for the Project on September 29, 2026 under the Federal Energy Regulatory Commission’s (FERC) Integrated Licensing Process (ILP). As part of the ILP, FERC will issue Scoping Document 1, which includes a process plan and schedule through submittal of the Final License Application. The Scoping Document and process plan identifies opportunities for stakeholder engagement during the relicensing process.